Course Code: BCE-503
Course: AKTU B.Tech 3rd Year, Semester V
Unit: Elements of Management and Network Techniques
Stream: Civil Engineering (CE)
Unit III Overview
Coordinate construction through project stages, organisation, WBS and time planning. Develop bar charts and networks; solve CPM and PERT; monitor and update the forecast; and allocate limited resources through worked building-project examples.
Topics Covered
| Syllabus area | Pages |
|---|---|
| Management, cycle and organisation | 2-5 |
| WBS, activities and charts | 5-8 |
| Network logic and representation | 8-10 |
| CPM timing and float | 10-11 |
| Integrated CPM and sensitivity | 11-13 |
| PERT and probability | 13-15 |
| Monitoring, updating and systems | 15-17 |
| Resources and schedule control | 17-19 |
| Solved problems and revision | 19-28 |
| PYQs with Answers | 29-47 |
Learning Outcomes
- 1. Explain the project cycle and site organisation.
- 2. Prepare WBS, bar charts and activity networks.
- 3. Calculate CPM times, float and critical paths.
- 4. Solve PERT mean, variance and probability.
- 5. Update forecasts and allocate limited resources.
Included in These Notes
44 explained sections; 33 labelled diagrams; 10 realistic construction images; integrated CPM and PERT cases; 26 solved problems; comparison tables; answered revision questions; a quick-reference sheet; and 25 fully answered, year-tagged PYQs (2020-21 to 2024-25).
Study Approach
Define the work. Decompose scope and assign clear outputs, roles and interfaces.
Draw the logic. Check immediate predecessors, durations, milestones and calendars.
Calculate and interpret. Use merge maxima, burst minima, float and probability assumptions.
Update and allocate. Verify actuals, recalculate forecasts and check resource capacity.
Key distinctions: a WBS is not a schedule; activity float is not event slack; an unlimited-resource CPM finish is not automatically resource-feasible. Preserve logic, actual history and the baseline.
1. Management as a construction decision system
Construction management coordinates people, methods, materials, equipment, information and money to deliver the agreed facility. A project must meet its scope and quality requirements while controlling time, cost, safety and environmental performance. Management is not only supervision of workers: design decisions, procurement, access, approvals and information flow can determine site output before a crew arrives.
The recurring functions are planning, organising, staffing, directing, coordinating and controlling. Planning sets objectives and methods; organisation allocates responsibility and authority; control compares evidence with the plan and initiates action. The functions interact throughout the project. Faster progress is not a success if it conceals defective work, unsafe operations or unapproved scope.
2. The construction project cycle
A typical cycle moves through need identification, feasibility, definition and design, approvals and procurement, mobilisation, construction, testing and commissioning, handover and closeout. Operation and maintenance follow and provide feedback for future projects. Stage names and overlaps vary with delivery strategy; design and procurement may proceed in controlled packages rather than wait for one complete sequential phase.
Each stage should have a clear output and a decision gate. Feasibility asks whether the project is justified; detailed planning establishes how the defined work can be delivered; closeout confirms completion and records outstanding obligations. A gate is a management decision, not necessarily a fixed-duration construction activity. Missing land access or an approval cannot be solved merely by drawing a later bar on a schedule.
3. Objectives, constraints and stakeholder interfaces
Translate the project purpose into measurable objectives: defined deliverables, acceptance criteria, milestones, budget boundaries and safety requirements. Identify constraints such as site access, utilities, approval dates, working hours, resource availability and seasonal conditions. Distinguish a required date from a forecast date; a desired completion does not prove that the current plan can achieve it.
Stakeholders include the employer, designer, contractor, subcontractors, suppliers, regulators, users and affected neighbours. Assign an owner to each interface. For example, a lift cannot proceed until the load is ready, the crane is available and the work zone is released. An interface register helps expose gaps that are easily missed when each department plans only its own tasks.
4. Organisation: authority, responsibility and communication
An organisation structure defines reporting relationships, decision authority and coordination channels. Responsibility describes the work or outcome assigned to a role; authority is the power to make the related decisions; accountability concerns answerability for the result. Delegation should provide enough authority and information for the assigned responsibility, within the governing contract and management controls.
A site organisation commonly has project management, planning, execution, quality, safety, commercial, procurement and administration functions. Roles need not correspond to separate full-time departments on a small job. Specify who prepares, reviews, approves and acts on an instruction so a change does not remain trapped between several equally informed people.
5. Functional, project and matrix arrangements
A functional arrangement groups people by specialism, such as design, procurement and finance. It promotes expertise and continuity but can create slow cross-functional decisions. A project arrangement places a dedicated team under a project manager and can improve coordination, although it may duplicate resources between projects.
A matrix combines functional expertise with project responsibility. It can share specialists effectively, but dual reporting requires clarity over priorities and authority. No structure is automatically best for every contractor or project size. Select a structure that matches complexity and interfaces, then define escalation paths so conflicting instructions are resolved promptly.
| Arrangement | Main advantage | Main limitation |
|---|---|---|
| Functional | Specialist depth and shared expertise | Cross-functional priorities may compete |
| Project | Clear project focus and coordination | Resources can be duplicated |
| Matrix | Combines shared skills with project focus | Dual authority requires explicit rules |
6. Responsibility matrix and coordination records
A responsibility matrix links work packages or decisions to named roles. A RACI form identifies the responsible doer, accountable owner, consulted parties and informed parties. For an unambiguous teaching matrix, assign one accountable owner per decision. Do not use a matrix to authorise actions beyond contractual or delegated powers.
Coordination records include drawing registers, request-for-information logs, meeting actions, procurement status and approvals. Each unresolved issue needs an owner, due date and effect on the plan. A meeting that merely records discussion without a decision or follow-up can consume time without reducing uncertainty.
7. Planning, scheduling, monitoring and updating
Planning determines what must be done, how it will be done and the resources and arrangements required. Scheduling places those activities in time while respecting logic, calendars and constraints. Monitoring collects evidence of actual performance. Updating incorporates actual status and credible remaining work into a fresh forecast.
Controlling uses the comparison to choose and follow up corrective action. These terms are related but are not interchangeable. A schedule update is not a new approved baseline unless the required change procedure authorises rebaselining. Keeping the original baseline visible preserves the ability to explain how the forecast has moved.
| Function | Core question | Typical output |
|---|---|---|
| Planning | What, how and with what resources? | Method, scope breakdown and resource plan |
| Scheduling | When and in what sequence? | Logic-linked dates and milestones |
| Monitoring | What has actually happened? | Verified status and records |
| Updating | What does current evidence predict? | Recalculated remaining schedule |
| Control | What action is needed? | Assigned corrective actions and follow-up |
8. Work breakdown structure: defining the scope
A work breakdown structure, or WBS, decomposes the project scope into manageable deliverables and work packages. For a small building it might separate substructure, superstructure, envelope, services, external works and handover. Lower levels identify the outputs needed to complete each parent element. Include all approved scope once, without omissions or overlapping ownership.
A WBS describes the work, not its time sequence and not who reports to whom. A floor package can be divided by location, discipline or deliverable if the structure remains clear and controllable. Stop decomposition at a level that can be assigned, estimated and tracked; an excessively fragmented WBS creates administration without better decisions.
9. Work packages, coding and the WBS dictionary
A work package needs a defined boundary, owner, deliverable, acceptance basis and interfaces. Its dictionary entry can identify inclusions, exclusions, drawings, quantities and required records. A hierarchical code such as 2.1.3 gives an address in the scope structure. It does not itself specify a predecessor relationship.
Use consistent codes across quantities, schedule, procurement and cost records so a work package can be traced between systems. Scope may be complete in the WBS while a schedule still omits necessary inspections or procurement activities. Convert each package into the tasks required to produce and accept its deliverable rather than simply renaming every WBS heading as one activity.
10. From work packages to a realistic activity list
Define an activity as a schedulable task with a clear completion criterion. Identify its quantity or scope, duration basis, predecessors, resources, location and responsible party. Suitable activities include setting out a block, excavating a trench reach, inspecting reinforcement, fabricating an assembly and completing a required test.
Avoid activities so broad that progress cannot be judged or so short that normal reporting cannot maintain them. Include off-site procurement and approvals when they govern site work. A steel frame cannot be erected merely because its erection crew is available if fabrication and delivery have not been planned.
11. Estimating duration and choosing a calendar
A first production estimate is duration = work quantity / achievable output rate. If 120 m³ is excavated at 30 m³ per working day, the calculated duration is four working days under that method and crew. Check mobilisation, access, inspections and other time requirements before treating that number as the complete elapsed duration.
Working days and calendar days are different. State working hours, weekends, holidays, shifts and any activity-specific calendar. A five-working-day task starting Monday at time zero finishes Friday’s work period on a Monday-to-Friday calendar, while its successor starts at the next permitted working instant. Numerical examples here use continuous working-day intervals unless a calendar is expressly stated.
12. Bar charts: constructing a readable schedule
A bar or Gantt chart places each activity against a time scale. The bar begins at the scheduled start and ends at the scheduled finish; its length represents duration. Add labels, units, a legend and a status date if progress is shown. Distinguish an activity bar from a milestone, which marks an event rather than a period of work.
Bar charts are easy to communicate and can show overlaps, baseline and actual performance. A simple unlinked bar chart does not by itself reveal every logical dependency or calculate float. Software can display linked logic in bar form, but the dependency model still needs separate checking. Never assume that two visually adjacent bars must have a finish-to-start relationship.
13. Milestone charts and management reporting
A milestone marks a significant event such as design approval, foundation acceptance, roof completion or handover. It is modelled as zero duration in a network schedule. A milestone chart highlights selected target and forecast dates for management, often leaving detailed activities to the supporting schedule.
Define the acceptance condition and responsible owner for every reported milestone. Roof complete may mean concrete placed, curing completed or structural release; those meanings produce different dates. Report the variance between the current forecast and the approved target. An approval task can take time; the milestone is the instant when the required approval has been achieved.
14. Network vocabulary and modelling assumptions
A network expresses the logical relationships among activities or events. A predecessor must satisfy the specified relationship before its successor can proceed. A path is a connected sequence through the network. A merge has more than one incoming dependency; a burst has more than one outgoing dependency.
The elementary CPM calculations in this unit assume non-negative fixed durations, finish-to-start links with zero lag, continuous working-day time and no resource limits unless a problem states otherwise. Use time zero at project start: a task from time 4 to time 9 lasts five days. This interval convention avoids the repeated plus-one errors caused by mixing date labels with elapsed durations.
15. Activity-on-node and activity-on-arrow
In activity-on-node, or AON, activities are boxes and the links express dependencies. In activity-on-arrow, or AOA, arrows represent activities and circles represent events. Events mark an instant and have no duration or resource use. Do not place an activity duration inside an AOA event and then treat the event as additional work.
Both representations can describe the same elementary logic. AON is convenient for activity-based start and finish calculations and richer precedence types. AOA is useful for event-time teaching and dummy activities. PERT is not inherently restricted to AOA, and CPM is not inherently restricted to AON; technique and drawing convention are different choices.
16. Preparing and checking network logic
Start with the activity list and immediate predecessors. Draw only the required dependencies, then check that every activity connects to the intended start and completion. A directed cycle is invalid in the ordinary project network: A cannot wait for B while B waits for A. Unintended open ends can hide work from the project completion calculation.
Keep physical requirements distinct from discretionary sequencing and resource choices. An inspection release is different from a planner’s preference to reuse one crew. Redundant links can clutter a diagram; deleting a true relationship to make the picture simpler creates an incorrect model. Network arrows convey logic, not distances or actual activity durations.
17. Dummy activities in an AOA network
A dummy is a zero-duration, zero-resource arrow used to preserve AOA logic or unique activity identification. It is often shown dashed. Suppose C depends only on A, while D depends on both A and B. A dummy can connect the finish event of A into the event from which D starts, without forcing C to wait for B.
A dummy is not a real inspection, waiting period or resource transfer. If a necessary wait lasts two days, it cannot be represented by a zero-duration dummy. Check the predecessor meaning after adding each dummy; a visually tidy network can still impose a false dependency.
18. Relationships, leads and lags
Finish-to-start means the successor cannot start until its predecessor finishes, with any stated lag. Start-to-start and finish-to-finish relationships constrain starts and finishes respectively. A start-to-finish relationship exists in some models but is less common in elementary construction examples. Positive lag introduces a minimum separation; a lead permits a defined overlap.
For A lasting four days and a finish-to-start lag of two days, a successor cannot start before time six if A begins at zero. Cure time should be made explicit and consistent with the specification; an arbitrary negative lag must not conceal unsafe overlap. When generalised relationships are used, apply the appropriate constraints rather than the simple zero-lag formulas unchanged.
19. CPM forward pass: earliest times
For an activity with duration d, earliest finish EF = ES + d. Its earliest start ES is the largest earliest finish among its immediate predecessors in the stated zero-lag model. A start activity has ES = 0 unless an external release constrains it. At a merge, all required predecessors must be complete, so the maximum governs.
Calculate in a valid topological order. The earliest finish of a single completion milestone is the project duration for this logic and its durations. This is a precedence-based lower bound when scarce resources have not yet been imposed. Choosing the minimum predecessor finish at a merge would allow work to start before all of its prerequisites are ready.
20. CPM backward pass: latest times
Anchor the final latest finish to the chosen completion time, normally the calculated earliest project finish in an unconstrained classroom CPM problem. For each activity, LS = LF – d. Its LF is the smallest latest start among its immediate successors. At a burst, every successor’s required start must remain feasible, so the minimum governs.
Move backwards through the network. A different imposed completion constraint can produce different float, including negative float where the target is earlier than the feasible forecast. Never compare floats obtained from different completion anchors as though they were calculated on the same basis.
21. Total float and the critical path
Total float TF = LS – ES = LF – EF in the elementary model. It is the delay available to an activity relative to the selected completion constraint, provided the connected schedule is treated consistently. With latest times anchored to the earliest project finish and no other constraints, activities on a critical path have zero total float.
The critical path is a longest-duration start-to-finish path. There can be more than one. Critical means schedule-controlling, not most expensive, most dangerous or most technically complex. A noncritical path can become critical after delay or acceleration elsewhere. Float on several activities of the same path is shared; it is not a collection of independent buffers that can all be spent twice.
22. Free, interfering and independent float
Free float is the delay that does not move the earliest start of an immediate successor. For AON zero-lag links, FF = minimum successor ES – activity EF; use the finish milestone for a terminal task. Interfering float is TF – FF and represents the portion that can affect successor timing without yet delaying the anchored project completion.
For an AOA activity i-j of duration d, TF = Lj – Ei – d and FF = Ej – Ei – d. A common non-negative independent-float definition is IF = max[0, Ej – Li – d]. State that convention, because some treatments first report the raw negative value. Independent float protects both the latest predecessor event and the earliest successor event; event slack itself is L – E.
23. Integrated CPM example: activity data
The following eight-activity teaching project contains parallel work and two merges. Its work packages are deliberately simplified to focus on scheduling rather than structural design. Durations are assumed working days. All relationships are finish-to-start with zero lag; all activities are required; resources are initially unlimited.
A and B begin at time zero. C and D wait for A. E waits for B. F requires both C and D; G requires both D and E; H requires both F and G. Read that logic from the predecessor table before performing arithmetic. In particular, F does not require E, and C does not require B.
| Activity | Duration; immediate predecessors |
|---|---|
| A | 4 d; none |
| B | 3 d; none |
| C | 5 d; A |
| D | 4 d; A |
| E | 6 d; B |
| F | 2 d; C, D |
| G | 3 d; D, E |
| H | 2 d; F, G |
24. Integrated CPM example: forward calculation
A: ES 0, EF 4. B: ES 0, EF 3. C follows A, so ES 4 and EF 9. D also follows A, so ES 4 and EF 8. E follows B, so ES 3 and EF 9. The parallel paths have different finishes even though several tasks started together.
F waits for C and D: ES = max(9,8) = 9; EF = 11. G waits for D and E: ES = max(8,9) = 9; EF = 12. H waits for F and G: ES = max(11,12) = 12; EF = 14. The precedence-only earliest project duration is therefore 14 working days.
25. Integrated CPM example: backward calculation
Set H’s LF to 14; therefore H has LS 12. F and G must finish by time 12, so F has LS 10 and G has LS 9. C must finish by F’s LS 10, giving C LS 5. D feeds F and G, so its LF = min(10,9) = 9 and LS = 5.
E feeds G, so E LF = 9 and LS = 3. A feeds C and D: LF = min(5,5) = 5, giving LS 1. B feeds E: LF = 3, giving LS 0. The use of the minimum at D’s burst is essential; choosing 10 would let D delay G.
26. Integrated CPM example: timing and float table
The calculated table provides an independent check against both passes. Subtract ES from LS to obtain TF. Subtract activity EF from the smallest successor ES to obtain FF. For example, D has TF = 5 – 4 = 1 and FF = min(9,9) – 8 = 1. A has TF 1 but FF 0 because its successors currently start immediately at time 4.
The zero-total-float chain is B-E-G-H, lasting 3 + 6 + 3 + 2 = 14 days. A-C-F-H and A-D-G-H each last 13 days, so both are near-critical at one day shorter. This does not mean each of their individual activities can independently consume one additional day with no cumulative effect.
| Act. | ES; EF | LS; LF | TF; FF |
|---|---|---|---|
| A | 0; 4 | 1; 5 | 1; 0 |
| B | 0; 3 | 0; 3 | 0; 0 |
| C | 4; 9 | 5; 10 | 1; 0 |
| D | 4; 8 | 5; 9 | 1; 1 |
| E | 3; 9 | 3; 9 | 0; 0 |
| F | 9; 11 | 10; 12 | 1; 1 |
| G | 9; 12 | 9; 12 | 0; 0 |
| H | 12; 14 | 12; 14 | 0; 0 |
27. Multiple critical paths and sensitivity to change
If E in the integrated example is shortened from six days to five, B-E-G-H becomes 13 days. Both A-C-F-H and A-D-G-H already last 13 days, so the project now has three critical paths at 13 days. Shortening E again would not reduce the project finish because the A-led paths still control it.
Likewise, increasing A from four to five days consumes the original one-day allowance and leaves project duration at 14 days. Increasing A to six days produces a 15-day finish. Recalculate the complete network after a change; the identity of the critical path is an output, not a permanent property attached to an activity name.
28. PERT: representing duration uncertainty
PERT uses three duration estimates: optimistic a, most likely m and pessimistic b, with a ≤ m ≤ b. They should refer to the same scope, crew, method and calendar. The traditional classroom expected duration is te = (a + 4m + b)/6. The most likely value receives four times the weight of either extreme.
The traditional approximate standard deviation is σ = (b-a)/6 and variance is σ² = [(b-a)/6]². These are modelling assumptions, not a proof that every construction activity follows an exact beta distribution or that the extremes are guaranteed limits. Keep the stated assumptions consistent and do not replace a pessimistic duration with an unrelated contractual deadline.
29. Expected-time networks and path variance
Calculate each activity’s expected duration and variance, then run the network using the expected durations. Identify the controlling expected-time path. For a stated fixed path with independent activity durations, its mean is the sum of means and its variance is the sum of variances. The path standard deviation is the square root of that variance sum.
Do not sum standard deviations or average variances along the path. If durations are correlated, covariance terms also matter. The duration of the whole project is the maximum over paths, so the longest expected-time path does not generally give an exact project-duration mean. The simple PERT estimate treats one controlling path as a useful approximation.
30. PERT completion probability and its limits
Under the stated fixed-path normal approximation, Z = (target time – path mean)/path standard deviation. The probability of finishing by the target is approximately Φ(Z), the normal cumulative probability to the left of Z. A target later than the mean produces a positive Z and a probability above 0.5 in this model.
For a target probability p, the corresponding time is approximately mean + zp × standard deviation. The result is a planning estimate, not a guarantee.
Multiple near-critical paths, correlated risks, skewed durations and few uncertain activities can make the simple approximation optimistic or otherwise inaccurate. More detailed risk modelling may be needed for a consequential completion commitment.
31. Integrated PERT example: a three-activity chain
Consider a serial chain P-Q-R with triplets P(2,4,6), Q(3,6,9) and R(1,2,3), all in days. Expected durations are 4, 6 and 2 days. Variances are 4/9, 1 and 1/9 day² respectively. The fixed-chain mean is 12 days; variance is 14/9 day²; standard deviation is approximately 1.2472 days.
For a 14-day target, Z = (14-12)/1.2472 ≈ 1.604. The approximate left-tail probability is 0.9456, or 94.56%. For an approximate 95% target using z = 1.645, time ≈ 12 + 1.645(1.2472) = 14.052 days. Use the adopted calendar and rounding policy when translating that into an operational date.
32. CPM and PERT: a practical comparison
Elementary CPM uses a single duration per activity and emphasises logical timing, float and critical paths. Traditional PERT adds three-point estimates and approximate uncertainty calculations. Both need an accurate activity list and logic, and both can be represented using suitable network diagrams. Neither technique makes a defective construction method feasible.
Avoid the claim that CPM applies only to construction and PERT only to research. Construction work can contain both repetitive tasks with stable production and uncertain tasks requiring risk estimates. Choose the method and detail according to the question being answered. Resource constraints and updating are necessary even when an original duration estimate appears precise.
| Aspect | Elementary CPM | Traditional PERT |
|---|---|---|
| Duration input | One stated duration | Three estimates a, m and b |
| Main calculations | Earliest/latest times and float | Expected times, variance and probability |
| Shared need | Correct scope and logic | Correct scope and logic |
| Main caution | Durations and resources remain assumptions | Single-path probability is approximate |
33. Establishing a baseline and a reporting date
A baseline records the approved schedule against which performance is compared. Preserve its logic, dates and assumptions through the agreed control system. A reporting or data date is the time boundary between recorded actual history and forecast remaining work. Every update should identify that date and the information used.
Record actual start and finish for completed work, progress and remaining duration for ongoing work, and expected releases for work not started. Data collection must distinguish actual evidence from a supervisor’s aspiration. Do not schedule unfinished work wholly before the status date or move actual history merely to make the new forecast look better.
34. Measuring progress and identifying variance
Measure physical progress using a defined basis such as accepted quantities, completed deliverables or weighted milestones. Money spent, time elapsed and physical completion are different quantities. A percentage without a denominator or acceptance basis is weak evidence. A task can consume most of its budget yet still lack a critical inspection or interface.
Compare baseline and actual or forecast dates, not only aggregate percentages. Report completed work, slippage, constraints, critical and near-critical work, resources and corrective actions. A large completed quantity on a noncritical activity cannot automatically compensate for a small but controlling delay on the critical path.
35. Updating the remaining network
Verify status, preserve completed actuals and estimate credible remaining durations. Review outstanding relationships, access, approvals and resources. Recalculate earliest and latest times for the remaining network from the status conditions, then compare the forecast finish with the baseline. Explain the cause and effect of material changes.
Out-of-sequence work needs explicit treatment. If a successor has partly started before its stated predecessor finished, inspect what portion can actually continue and which dependency remains. Do not blindly erase the link or force a software result without reviewing the construction logic. Keep a record of any approved change in sequence.
36. Update example: a delayed activity changes the forecast
In the eight-activity example, assume A actually takes six days rather than four, B finishes at time 3, and all other stated durations and logic remain unchanged. At the time-6 update, C and D can start. C finishes at 11, D at 10 and E at 9; therefore F runs 11-13, G runs 10-13 and H runs 13-15.
The current forecast is 15 days, one day later than the 14-day baseline. The two days added to A use one day of original path allowance and produce one day of project delay. The controlling A-C-F-H and A-D-G-H paths both last 15 days under these new durations. The baseline is preserved while the current forecast is reported separately.
37. Construction management information systems
A management information system connects the WBS, schedule, quantities, procurement, cost, quality, safety and change records so managers can act on consistent evidence. A drawing revision or material delay should be linked to the affected work package and activity, rather than remain an isolated file in a different department.
Define data owners, update frequency, coding, review and approval rights, version control and report distribution. A digital dashboard does not improve control if its inputs are stale or inconsistent. Use a concise exception report to highlight the decision required, responsible person and due date. Protect the approved baseline and actual records from casual overwriting.
38. Resource loading and the resource histogram
Resource loading assigns a crew, plant, material or other demand to an activity over its scheduled period. Sum simultaneous demands to form a time-phased resource profile. A resource histogram displays that demand by period; a capacity line shows availability. An overload exists when required demand exceeds the available capacity in a period.
State whether the resource is renewable, such as workers available each day, or consumable, such as a fixed material stock. Specify constant or variable activity demand. A network feasible with unlimited resources may not be executable with one crane, one specialist crew or limited work space. Resource checking therefore follows, rather than replaces, logical network checking.
39. Allocation, smoothing and resource-constrained levelling
Allocation assigns resources to activities and time periods. In a time-constrained smoothing exercise, move suitable noncritical work within available float to reduce peaks while preserving the required finish and dependencies. In a resource-constrained levelling exercise, respect capacity even if that requires a later finish. Terminology can vary, so state the operational objective clearly.
A resource adjustment can change critical paths and float. After shifting an activity, recalculate the consequences rather than continuing to spend its original float elsewhere. Merely drawing a lower histogram by deleting demand is not levelling; the same work, duration and resource requirements must still be delivered unless an approved method change justifies them.
| Decision | Priority | Possible consequence |
|---|---|---|
| Loading | Represent activity demand | Reveals period-by-period overload |
| Smoothing | Meet finish using available float | Peaks reduced without extending target |
| Resource-constrained levelling | Respect fixed capacity | Project finish may move later |
| Method change | Alter justified production arrangement | New duration, resources and risks need checking |
40. Smoothing example: moving work within float
A lasts four days and precedes B, which lasts four days. Independent C lasts three days and must also finish before the project completion. A requires three workers, B one worker and C two workers. The precedence-only finish is eight days; C can move within five days of total float.
At earliest starts, A and C overlap from time 0 to 3 and require five workers. Shift C to time 4-7, alongside B. Demand becomes three workers from 0-4, three from 4-7 and one from 7-8. The peak falls from five to three while the eight-day finish and all dependencies are preserved.
41. Resource-constrained example: capacity changes completion
Independent X and Y last four and three days respectively, and both precede Z, which lasts two days. X and Y each require three workers; Z requires two. Unlimited-resource CPM gives max(4,3)+2 = 6 days, but running X and Y together requires six workers.
With capacity limited to three and nonpreemptive activities using their stated crews, X and Y must be sequenced. X at 0-4, Y at 4-7 and Z at 7-9 gives a feasible nine-day schedule. Reversing X and Y also gives nine days here. A six-day target is infeasible under these assumptions without changing capacity, crew demand or the construction method.
42. Priority rules and practical resource decisions
When several eligible activities compete for a scarce resource, a heuristic can give priority to least total float, earliest required finish, shortest duration or another stated rule. Apply the chosen tie-breakers consistently. No simple priority rule guarantees the optimal schedule for every resource-constrained project.
Check mobilisation, continuity, safe working space, trade interference, storage and supervision before approving a resource move. Splitting an activity into fragments may not be physically practical. Separate a feasible schedule from an optimal one: a plan can respect all constraints yet still admit an improvement after a better allocation is found.
43. Recovery measures, crashing and fast tracking
Recovery can remove constraints, improve sequencing, add suitable resources or adopt a justified method. Crashing reduces an activity’s duration at an assessed extra direct cost; fast tracking overlaps work that was originally sequential where the technical and contractual logic allows it. Both can increase risk and must preserve quality and safety.
For a linear classroom crash model, cost slope = (crash cost – normal cost)/(normal duration – crash duration). Reduce critical work only where that actually reduces the project duration, and recheck all paths after each change. With multiple critical paths, crashing one path alone may produce no project saving. Detailed project cost optimisation belongs to the cost-management unit; the present purpose is schedule-control reasoning.
44. Network audit and common examination mistakes
Audit activity completeness, immediate predecessors, durations, time units, calendars, start and completion connectivity, merge maxima, burst minima, float and resource limits. Verify a longest path independently after calculating the timing table. A wrong input will still produce a mathematically tidy software schedule.
Frequent mistakes are adding one day to every elapsed-time interval, choosing the minimum in a forward merge, summing all parallel durations, treating a dummy as real work, adding standard deviations, counting shared float repeatedly and assuming unlimited-resource CPM is resource-feasible. Finish each answer with interpretation: identify the controlling path, completion basis, practical constraint and any approximation used.
SOLVED PROBLEMS: CPM, PERT AND RESOURCES
All durations, resources and costs are assumed teaching data. Unless stated otherwise, use time-zero elapsed working-day intervals, FS links with zero lag and unlimited resources. PERT probabilities use the expressly stated approximation.
Worked problem 3.1: Quantity-to-duration conversion
Question. Excavation quantity is 120 m³. One planned crew achieves 30 m³ per working day. Assume uninterrupted output and no additional mobilisation period. Find duration.
- 1. Duration=quantity/output=120/30=4 working days.
- 2. Check dimensions: m³ divided by m³/day gives days.
- 3. A different calendar or access restriction would affect the elapsed dates, not this arithmetic.
Answer. 4 working days under the stated assumptions.
Check. Do not multiply quantity by output or silently substitute calendar days.
Worked problem 3.2: Elapsed-time bars without a plus-one error
Question. A starts at time 2 and lasts 4 days. B lasts 3 days and follows A immediately. Use continuous working-day time. Find both finishes and total elapsed time from project time zero.
- 1. A finishes at 2+4=6. Its interval is 2-6.
- 2. B starts at 6 and finishes at 6+3=9.
- 3. The work sequence occupies 7 days from its start at time 2; the finish measured from project zero is time 9.
Answer. A EF=6; B ES=6, EF=9.
Check. No extra one-day gap is inserted between adjacent intervals.
Worked problem 3.3: Forward pass at a merge
Question. C lasts 4 days and requires A and B. A finishes at time 8, B at time 11. Find C’s earliest interval.
- 1. Both predecessors must be complete.
- 2. C ES=max(8,11)=11.
- 3. C EF=11+4=15.
Answer. C runs 11-15.
Check. Using min(8,11) would start C three days before B is ready.
Worked problem 3.4: Backward pass at a burst
Question. D lasts 4 days and feeds successors whose latest starts are 12 and 9. Find its LF and LS.
- 1. D must finish early enough for both successors.
- 2. LF=min(12,9)=9.
- 3. LS=9-4=5.
Answer. LF=9; LS=5.
Check. The smaller successor latest start controls the burst.
Worked problem 3.5: A small parallel CPM network
Question. A lasts 3 days and precedes C of 4 days. B lasts 5 days and precedes D of 3 days. E lasts 2 days and follows C and D. A and B start at zero. Find completion and the critical path.
- 1. A-C finishes at 3+4=7; B-D finishes at 5+3=8.
- 2. E ES=max(7,8)=8, so EF=10.
- 3. Path A-C-E lasts 9 days; B-D-E lasts 10 days.
Answer. Project 10 days; critical path B-D-E.
Check. Do not sum A, B, C, D and E as if all five were serial.
Worked problem 3.6: Integrated example: forward merge calculations
Question. Use the eight-activity project in the main text. C EF=9, D EF=8, E EF=9. F lasts 2 days after C,D; G lasts 3 days after D,E; H lasts 2 days after F,G. Find the finish.
- 1. F ES=max(9,8)=9; EF=11.
- 2. G ES=max(8,9)=9; EF=12.
- 3. H ES=max(11,12)=12; EF=14.
Answer. Finish at time 14.
Check. Every required predecessor participates in its merge calculation.
Worked problem 3.7: Integrated example: total and free float
Question. For D, ES=4, EF=8, LS=5, LF=9. Successor earliest starts are F=9 and G=9. Find total, free and interfering float.
- 1. TF=LS-ES=5-4=1 day, also LF-EF=9-8=1.
- 2. FF=min(9,9)-8=1 day.
- 3. Interfering float=TF-FF=1-1=0.
Answer. TF=1; FF=1; interfering float=0 days.
Check. D can slip one day without moving either successor’s earliest start in this unchanged schedule.
Worked problem 3.8: Float that affects a successor
Question. For A in the integrated example, ES=0, EF=4, LS=1 and successor C,D earliest starts are both 4. Find TF and FF and interpret a one-day delay.
- 1. TF=1-0=1 day.
- 2. FF=min(4,4)-4=0.
- 3. Delaying A by one day moves its successors, but the anchored project finish remains 14 days after the network is recalculated.
Answer. TF=1 day; FF=0.
Check. No free float does not necessarily mean no total float.
Worked problem 3.9: AOA float and event slack
Question. An AOA activity i-j lasts 4 days. Ei=3, Li=5, Ej=10 and Lj=13. Find TF, FF, independent float under a non-negative convention, and both event slacks.
- 1. TF=13-3-4=6 days. FF=10-3-4=3 days.
- 2. IF=max(0,10-5-4)=1 day. Interfering float=6-3=3 days.
- 3. Tail-event slack=5-3=2; head-event slack=13-10=3 days.
Answer. TF 6; FF 3; IF 1; event slacks 2 and 3 days.
Check. Event slack is not the same as activity total float.
Worked problem 3.10: A negative raw independent-float value
Question. An activity has Ej=9, Li=7 and duration 4. Find independent float using IF=max(0,Ej-Li-d).
- 1. Raw expression=9-7-4=-2 days.
- 2. The adopted non-negative convention truncates it at zero.
- 3. IF=max(0,-2)=0.
Answer. Independent float=0 days under the stated convention.
Check. State the convention; some treatments report the raw negative expression before truncation.
Worked problem 3.11: AOA dummy logic and event timing
Question. A is 1-2 with duration 3. B is 1-3 with duration 4. A dummy 2-3 has duration zero. C is 2-4 with duration 2 and D is 3-4 with duration 3. Start event 1 is at zero. Find event times and explain the dummy.
- 1. E_2=0+3=3. E_3=max(0+4,3+0)=4.
- 2. E_4=max(3+2,4+3)=7.
- 3. C requires A only; D requires A and B because event 3 receives the real B arrow and the dummy from A.
Answer. Event times 0,3,4,7; project duration 7 days.
Check. The dummy contributes logic but no time, cost or resource demand.
Worked problem 3.12: A finish-to-start lag
Question. A begins at time 1 and lasts 4 days. B lasts 3 days and has an FS+2 relationship from A. Find B’s earliest finish.
- 1. A EF=1+4=5.
- 2. B ES=A EF+lag=5+2=7.
- 3. B EF=7+3=10.
Answer. B runs 7-10.
Check. The lag is an explicitly stated minimum separation; it is not an additional work quantity.
Worked problem 3.13: A path becomes jointly critical
Question. Original integrated project has B-E-G-H=14 days and both A-C-F-H and A-D-G-H=13 days. Reduce E by one day and change nothing else. Find project duration and critical paths.
- 1. B-E-G-H becomes 13 days.
- 2. The two A-led paths remain 13 days.
- 3. All three now control a 13-day finish.
Answer. 13 days with three critical paths.
Check. Reducing E by a second day alone will not reduce the project below 13 days.
Worked problem 3.14: Shared path float cannot be spent twice
Question. A noncritical serial path A-B lasts 2+3=5 days. A parallel controlling path lasts 7 days. If A is delayed by 1 day and B then takes 2 extra days, with no other changes, find the finish.
- 1. Original path allowance=7-5=2 days.
- 2. Combined path increase=1+2=3 days; new A-B path=8 days.
- 3. New project finish=max(8,7)=8 days.
Answer. Project delay=1 day.
Check. The original two days are shared along the path, not separately available to every activity.
Worked problem 3.15: Update after A takes six days
Question. In the integrated project, set A duration to 6 while B remains 3 and all other durations and logic stay unchanged. Find the revised completion and critical paths.
- 1. C=6-11, D=6-10 and E=3-9.
- 2. F=max(11,10) to +2 → 11-13. G=max(10,9) to +3 → 10-13.
- 3. H=13-15. Paths A-C-F-H and A-D-G-H both total 15 days.
Answer. Forecast 15 days, one day later than the baseline.
Check. The two-day increase in A consumes one day of original allowance and adds one day to completion.
Worked problem 3.16: Three-point activity estimate
Question. For one activity, a=2, m=5 and b=8 days. Find traditional PERT mean, standard deviation and variance.
- 1. te=(2+4 × 5+8)/6=30/6=5 days.
- 2. σ=(8-2)/6=1 day.
- 3. Variance=1²=1 day².
Answer. Mean 5 days; σ=1 day; variance=1 day².
Check. Variance has squared time units. It is not an additional duration to add to the mean.
Worked problem 3.17: An asymmetric three-point estimate
Question. For an activity, a=2, m=3 and b=10 days. Find traditional expected time and variance.
- 1. Expected time=(2+4 × 3+10)/6=24/6=4 days.
- 2. Standard deviation=(10-2)/6=4/3 days.
- 3. Variance=(4/3)²=16/9≈1.7778 day².
Answer. Expected time 4 days; variance approximately 1.7778 day².
Check. The expected value need not equal the most likely time when the three estimates are asymmetric.
Worked problem 3.18: PERT serial-chain aggregation
Question. Independent activities P,Q,R have means 4,6,2 days and variances 4/9,1,1/9 day². Find chain mean, variance and standard deviation.
- 1. Mean=4+6+2=12 days.
- 2. Variance=4/9+1+1/9=14/9≈1.5556 day².
- 3. Standard deviation=√(14/9)≈1.2472 days.
Answer. Mean 12; variance 1.5556; σ approximately 1.2472 days.
Check. Add variances, not standard deviations. The assumed independence is required for this simple sum.
Worked problem 3.19: Probability of meeting a 14-day deadline
Question. Use the preceding chain and assume its total duration is approximately normal. Find probability of completing by day 14. Use Φ(1.604)≈0.9456.
- 1. Z=(14-12)/1.2472≈1.604.
- 2. Completion by the target corresponds to the left-tail cumulative probability.
- 3. P(T≤14)≈Φ(1.604)≈0.9456.
Answer. Approximately 94.56% under the stated fixed-chain normal model.
Check. For a branched project, a single expected critical path can be optimistic; this question explicitly uses one chain.
Worked problem 3.20: A target for approximately 95% completion
Question. For the same chain, use z_0.95=1.645. Find the continuous-time 95% target.
- 1. Target=mean+z × σ.
- 2. T≈12+1.645 × 1.2472≈14.052 days.
- 3. If a whole working-day commitment is required and only upward rounding is permitted, choose day 15 rather than rounding down to 14.
Answer. Approximately 14.052 days; day 15 under the stated whole-day rule.
Check. A probabilistic target is not a guarantee of completion.
Worked problem 3.21: Probability within a symmetric time interval
Question. For the same approximately normal chain, find P(10≤T≤14). Both limits are two days from the mean. Use Φ(1.604)=0.9456.
- 1. Upper Z≈1.604; lower Z≈-1.604.
- 2. By symmetry, Φ(-1.604)=1-0.9456=0.0544.
- 3. Interval probability=0.9456-0.0544=0.8912.
Answer. Approximately 89.12%.
Check. Use the difference of two cumulative probabilities, not their sum.
Worked problem 3.22: Resource smoothing and conserved effort
Question. A runs 0-4 with 3 workers; B follows A at 4-8 with 1 worker. Independent C lasts 3 days with 2 workers and must finish by time 8. Compare C at 0-3 and at 4-7.
- 1. Early placement peak=3+2=5 workers during 0-3.
- 2. Shifted placement demand=3 workers during 0-4, 3 during 4-7 and 1 during 7-8. Peak=3.
- 3. Effort remains 4 × 3+4 × 1+3 × 2=22 worker-days. Finish remains time 8.
Answer. Peak reduces from 5 to 3; effort 22 worker-days; finish unchanged.
Check. The shift changes timing, not resource quantities or activity duration.
Worked problem 3.23: Resource capacity extends the schedule
Question. X=4 days and Y=3 days are independent and each needs 3 workers. Both precede Z=2 days with 2 workers. Capacity is 3; tasks are nonpreemptive and crew sizes fixed. Find unlimited and resource-feasible durations.
- 1. Unlimited CPM=max(4,3)+2=6 days, but X+Y would need 6 workers.
- 2. Sequence X 0-4, Y 4-7, Z 7-9 to respect capacity.
- 3. The total X+Y duration must be 7 days because they cannot overlap under these assumptions. Z then needs 2 more days.
Answer. Unlimited duration 6 days; minimum feasible duration 9 days for this stated case.
Check. Adding a capacity limit can change both completion and the controlling sequence.
Worked problem 3.24: Weighted physical progress
Question. Package A has planned value ₹2 lakh and package B ₹3 lakh. Accepted physical completion is A 50%, B 20%. Use these planned-value weights only to calculate aggregate physical progress. Actual expenditure is ₹4 lakh.
- 1. Weighted completed value=2 × 0.50+3 × 0.20=1.60 lakh.
- 2. Total defined value=2+3=5 lakh.
- 3. Weighted progress=1.60/5 × 100=32%.
Answer. 32% on the stated weighting basis.
Check. Spending ₹4 lakh does not mean 80% physical completion. Price weights and acceptance rules must be defined.
Worked problem 3.25: Forecast remaining duration from quantity
Question. A work item contains 100 units; 60 accepted units are complete at the status date. Credible future output is 8 units per day. Assume no new access or mobilisation restriction. Find remaining duration.
- 1. Remaining quantity=100-60=40 units.
- 2. Remaining duration=40/8=5 working days.
- 3. Place the remaining work after the status date under its actual release conditions.
Answer. 5 working days remaining.
Check. Do not infer remaining duration solely from the original time percentage when the output rate has changed.
Worked problem 3.26: Crash slope and network effect
Question. A critical activity has normal duration 4 days and direct cost ₹4,000; crash duration 2 days and cost ₹7,000. Assume a linear cost-duration relation. Find slope and cost to reduce it by one day; explain the project-duration condition.
- 1. Slope=(7000-4000)/(4-2)=₹1,500 per day reduced.
- 2. One-day reduction adds ₹1,500, making direct activity cost ₹5,500.
- 3. The project gains a day only if no other path or constraint continues to control the old finish.
Answer. Slope ₹1,500/day; one-day-crashed activity cost ₹5,500.
Check. After crashing, recompute all paths; activity shortening is not automatically project shortening.
QUICK REVISION: ANSWERS WITH REASONS
What is construction management intended to coordinate?
Scope, people, methods, resources and information so the required facility is delivered with controlled time, cost, quality and safety.
Is the project cycle a single rigid sequence?
No. Stages can overlap by delivery strategy, but their outputs, approvals and interfaces still need definition.
How does authority differ from responsibility?
Authority permits specified decisions; responsibility assigns work or outcomes. Both must be aligned.
What does a matrix organisation combine?
Functional specialism with project coordination; dual priorities require explicit authority rules.
What does the WBS describe?
The full approved scope in a hierarchy of deliverables and work packages, with each part included once.
Is the WBS an organisation chart or schedule?
No. It defines work; organisation allocates roles; the schedule defines sequence and timing.
What makes an activity measurable?
A defined scope, completion criterion, duration basis, responsible owner and traceable progress evidence.
What distinguishes a milestone?
It marks a significant event or achievement with zero duration in the network.
What is the limitation of an unlinked bar chart?
It communicates dates well but does not itself calculate complete dependency logic, criticality and float.
What does an AOA event consume?
No time or resources; it represents an instant of achievement.
Why add a dummy activity?
To preserve required AOA logic or unique activity identification without adding time or resources.
Can the normal project network contain a directed cycle?
No. Circular dependencies prevent a valid topological calculation.
Which value governs a forward-pass merge?
The largest predecessor earliest finish in the elementary zero-lag model.
Which value governs a backward-pass burst?
The smallest successor latest start in that same model.
What is the critical path?
A longest-duration path governing the precedence-only completion under the stated assumptions.
Can there be several critical paths?
Yes. Equal controlling paths can coexist, and all must be considered in a recovery plan.
Does critical mean expensive or dangerous?
No. Schedule criticality is different from cost importance or safety risk.
Why is float shared?
Delays on connected activities can consume the same path allowance; it cannot be counted independently at each activity.
How does free float differ from total float?
Free float preserves immediate successor earliest starts; total float preserves the selected project completion constraint.
What is event slack?
The event latest time minus its earliest time; it is not automatically the float of an attached activity.
What are the traditional PERT time estimates?
Optimistic a, most likely m and pessimistic b, defined for the same activity scope and method.
Can path standard deviations be added directly?
No. Under independence, add path variances, then take the square root.
Why is simple PERT probability approximate?
It usually models one controlling path with assumed independence and an approximate normal total, while other paths and correlations can matter.
What is the data date?
The update boundary between verified actual history and forecast remaining work.
Does updating erase the baseline?
No. The current forecast changes; the baseline changes only through the authorised procedure.
Can spending percentage stand in for physical progress?
No. Spending, accepted physical completion and elapsed time measure different things.
Why review out-of-sequence work?
The actual portion completed and the remaining technical dependency must be understood before recalculating.
What does resource loading show?
Activity demand over its scheduled periods, summed into a resource profile.
What is the purpose of smoothing in these notes?
Move suitable work within float to improve the resource profile while preserving the required finish.
Can resource-constrained levelling extend completion?
Yes. A fixed capacity can make the unlimited-resource CPM finish infeasible.
Does a priority rule guarantee an optimal allocation?
No. It is a stated heuristic for choosing between eligible competing activities.
What must follow a crash decision?
Recalculate all paths, check remaining constraints and review cost, safety, quality and resource effects.
EXAM-STYLE QUESTIONS WITH ANSWERS
Explain the construction project cycle and organisation.
A project begins with a defined need and feasibility, then moves through scope definition, design, approvals, procurement, mobilisation, construction, testing and handover. Closeout records completion and outstanding obligations; operational experience feeds later projects. Stages can overlap, so each package needs clear information, release and acceptance interfaces.
Organisation assigns authority, responsibility and communication. Functional structures retain expertise, project structures improve dedicated coordination and matrix structures combine the two while requiring clear priority rules. Establish named owners for planning, execution, commercial, quality, safety and procurement decisions. Link work-package responsibilities to approvals and records; a chart alone does not resolve an unassigned interface.
Describe preparation of a WBS and a network schedule.
Define the approved project scope and decompose it into deliverables, then controllable work packages. Include all required work once. Record boundaries, acceptance, owner and interfaces in the dictionary. The WBS is a scope hierarchy, not the activity sequence or reporting hierarchy.
Develop the activities needed to produce and accept those packages. Estimate durations and resources on a stated calendar; identify immediate predecessors and release conditions. Draw a valid AON or AOA network, using zero-duration dummies only when needed for AOA logic. Check completeness, start-to-finish connectivity, cycles, unintended dependencies and procurement or approval tasks before calculating dates.
Explain CPM forward pass, backward pass and float.
With fixed durations and zero-lag finish-to-start links, set each ES to the maximum EF of immediate predecessors and calculate EF=ES+d. The final earliest finish gives the precedence-only duration. Anchor the final LF to that completion, then set each predecessor LF to the minimum successor LS and calculate LS=LF-d.
Total float is LS-ES or LF-EF. Free float is the smallest successor ES minus activity EF. A longest path has zero total float under the stated unconstrained completion anchor. In the integrated example, B-E-G-H takes14 days; two A-led paths take13. Float is shared along connected logic, and resource limitations can invalidate the simple earliest-start allocation.
Explain traditional PERT probability calculations.
Obtain consistent optimistic, most likely and pessimistic durations a,m,b. Calculate te=(a+4m+b)/6 and variance=[(b-a)/6]². Use the expected times in the network to identify the controlling expected path. For a fixed path with independent durations, add its means and variances and take the square root of the variance sum.
Under the approximate normal model, Z=(target-mean)/standard deviation and completion by the target uses the left-tail cumulative probability. An inverse target is mean+zp×standard deviation. State the assumptions. Other near-critical paths can control actual completion, and correlated risks require covariance terms; the simple single-path result is not a guaranteed project forecast.
Describe monitoring, updating and construction information systems.
Establish an approved baseline and an identifiable status date. Collect accepted quantities, actual starts and finishes, remaining durations, resource availability and constraints. Compare actual and forecast performance with targets, distinguishing physical work, money spent and time elapsed.
Preserve actual history, review remaining logic and out-of-sequence work, and recalculate the forecast. Explain any movement of the critical path and finish. Record actions with owners and due dates. An information system links WBS codes, drawings, procurement, cost, quality, safety and changes. Data ownership, version control and approval rights matter more than the appearance of a dashboard.
Compare resource smoothing and resource-constrained scheduling.
First load activities with defined demand and sum simultaneous requirements in a histogram. Compare with capacity. For a time-constrained smoothing problem, move noncritical work within available float while retaining the finish and all dependencies. In the smoothing example, shifting a three-day activity from0-3 to4-7 reduces the peak from five to three workers without changing the eight-day finish.
If capacity is fixed and float cannot absorb the conflict, levelling may extend completion. Independent X and Y need the same three-person crew for four and three days, followed by a two-day joint successor. Unlimited-resource completion is six days; capacity three forces a nine-day sequence. Recalculate criticality and float after allocation. A heuristic rule gives a feasible priority, not a universal proof of optimum.
Explain a logical approach to schedule recovery.
Confirm the actual constraint before choosing a remedy. Resolve approvals, access or materials issues; inspect whether work can be resequenced safely; consider additional capacity or a different method. Crashing shortens a duration at extra assessed cost; fast tracking overlaps suitable work and can raise rework or coordination risk.
Check all controlling and near-critical paths. A saving on only one of several critical paths may leave project completion unchanged. Recalculate the network and resource plan after each proposal and retain the approved baseline for comparison. Assess safety, quality, contractual approvals and practical access before accepting a recovery date. Report both the action and the evidence needed to verify its benefit.
CPM AND NETWORK QUICK REFERENCE
| Concept | Relation and stated scope |
|---|---|
| Duration | Quantity ÷ achievable output rate |
| Earliest finish | EF=ES+d |
| Forward merge | ES=max(predecessor EF) |
| Latest start | LS=LF-d |
| Backward burst | LF=min(successor LS) |
| Total float | TF=LS-ES=LF-EF |
| Free float, AON | FF=min(successor ES)-EF |
| Interfering float | TF-FF |
| Event slack | L-E |
| AOA total float | Lj-Ei-d |
| AOA independent float | max(0,Ej-Li-d) |
INTEGRATED CPM: FINAL CHECK VALUES
| Result | Original example |
|---|---|
| Project finish | 14 working days |
| Critical path | B-E-G-H |
| Near-critical paths | A-C-F-H; A-D-G-H: 13 d |
| D total and free float | 1 d; 1 d |
| A total and free float | 1 d; 0 d |
| E reduced by 1 d | 13 d, three critical paths |
| A increased to 6 d | 15 d, two critical paths |
Forward: maximum at a merge. Backward: minimum at a burst. Float is shared along connected logic; recalculate after a change.
PERT AND RESOURCES QUICK REFERENCE
| Concept | Relation and stated scope |
|---|---|
| PERT mean | (a+4m+b)/6 |
| PERT activity variance | [(b-a)/6]² |
| Independent path mean | Sum of activity means |
| Independent path variance | Sum of activity variances |
| Path standard deviation | Square root of path variance |
| Normal completion score | Z=(target-mean)/σ |
| Probability target | T≈mean+zp×σ |
| Resource demand | Sum of concurrent activity demands |
| Linear crash slope | Extra direct cost ÷ time reduced |
PERT CHAIN: FINAL CHECK VALUES
| Result | P-Q-R example |
|---|---|
| Mean | 12 d |
| Variance; standard deviation | 14/9 d²; 1.2472 d |
| P(T ≤ 14 d) | Approx. 94.56% |
| Approximate 95% target | 14.052 d |
| Resource smoothing case | Peak 5 → 3; finish 8 d |
| Resource-limited case | Finish 6 → 9 d |
PYQs WITH ANSWERS – UNIT III
Questions from the five supplied papers, grouped by examination session, with original numbers, marks and answers. Clear redrawings preserve the activity connections and supplied durations for questions that require networks.
| Marks | Theory target | What to include |
|---|---|---|
| 2 | 40-60 words | Direct definition or requested points; a unit, formula or example where useful. |
| 7 | 150-200 words | A short introduction, organised explanation or comparison, and a relevant example or sketch. |
| 10 | 250-300 words | A complete structured explanation, key distinctions and a relevant example, table or diagram. |
Writing guide: These are practical targets, not prescribed AKTU word limits. Follow the exact question and any examiner instruction. For numericals, prioritise given data, assumptions, formula, substitution, units and the final result; do not add prose merely to meet a word count. Tables and diagrams replace unnecessary sentences.
EXAMINATION 2020-21 | KCE503
Q1 (2020-21)
Original Q1(g) | Section A | 2 marks
Define most likely time and mean time.
Answer
Most likely time (m) is the activity duration expected under normal working conditions and is the modal estimate. Mean time is the PERT weighted expected duration, te = (a + 4m + b)/6, where a and b are optimistic and pessimistic estimates. It need not equal m.
Q2 (2020-21)
Original Q2(d) | Section B | 10 marks
Illustrate the CPM techniques as used in scheduling a construction project. Also give the difference between PERT and CPM system.
Answer
The critical path method represents the work as a precedence network and finds the longest-duration route from start to completion. It establishes the earliest feasible completion under the stated logic, durations, calendars and resource assumptions.
Procedure for a construction project
1. Define the work: Break the building into measurable activities such as excavation, foundations, frame, services and finishes. State a consistent time unit, estimate durations and identify immediate predecessors. Distinguish the work breakdown from the sequence of execution.
2. Draw and validate the network: Connect activities according to technical dependencies. Provide a clear start and finish, avoid loops and check interfaces. Use dummy activities only when an activity-on-arrow representation needs them to preserve logic.
3. Calculate early and late times: Run a forward pass using the maximum incoming finish at each merge. Run a backward pass from the project finish using the minimum outgoing latest start at each burst. Tabulate activity ES, EF, LS and LF.
4. Identify the critical route: Compute total float as LS – ES or LF – EF. Activities with zero total float form the critical route for an unconstrained earliest-finish schedule. A critical delay ordinarily delays completion unless recovery or changed logic offsets it.
5. Use and update the schedule: Compare actual progress with the baseline, revise remaining durations and recalculate criticality. Check resource capacity before promising the mathematical finish; CPM alone does not resolve crew conflicts.
PERT and CPM comparison
| Basis | CPM | PERT |
|---|---|---|
| Activity duration | Usually one deterministic estimate | Three estimates; weighted mean and variance |
| Emphasis | Time control and time-cost trade-off | Uncertain durations and completion probability |
| Typical use | Repetitive, better-defined construction work | Work with substantial duration uncertainty |
For example, excavation → foundation → frame may govern completion while procurement runs in parallel. Both techniques require sound dependencies and realistic updates; neither makes an inaccurate activity estimate reliable.
Q3 (2020-21)
Original Q6(a) | Section C | 10 marks
Explain bar chart. What were the problems in the bar charts that lead to development of network technique?
Answer
A bar chart, or Gantt chart, is a time-scaled schedule in which activities occupy separate rows and horizontal bars show planned start, duration and finish. It communicates the timing of construction work in a form that site teams can read quickly.
1. Preparation: List the activities, estimate their durations and decide the necessary execution sequence. Select a daily or weekly scale, place each bar against its time interval and identify important completion milestones. State whether dates use calendar days or working days.
2. Reading the chart: The left end of a bar shows commencement, its length shows duration and the right end shows completion. Parallel bars indicate overlap. Shade completed portions or add a separate actual-progress bar to compare performance with the approved plan.
3. Example: Suppose setting out takes days 0-2, excavation days 2-6 and foundation concrete days 6-9. Material procurement can occupy days 0-5. The construction chain finishes at day 9, while procurement must finish before the operation that requires those materials.
Problems that encouraged network techniques
4. Dependencies are not explicit: An ordinary bar chart may show dates without explaining which technical predecessor controls each start. A revised bar therefore gives little guidance about all the affected successors.
5. Criticality and float are unclear: A visually long bar is not necessarily critical. Ordinary charts do not calculate shared float, event slack or the longest connected path, so managers may concentrate on the wrong activity.
6. Updates become difficult: Delays, alternative sequences and numerous interdependent activities require repeated manual adjustment. The consequence of a changed duration is difficult to trace consistently across a large project.
CPM and PERT address these weaknesses through explicit logic, forward and backward passes and float analysis. Modern linked Gantt charts combine a readable time display with an underlying network; the limitation concerns an unlinked conventional bar chart.
Q4 (2020-21)
Original Q6(b) | Section C | 10 marks
Explain the principles of planning. State their advantages and limitations.
Answer
Planning determines what must be achieved, how the work will be performed, who is responsible and what resources are required. Scheduling subsequently assigns times to this plan. Effective construction planning is a continuous management process rather than a document prepared only at mobilisation.
1. Clear objectives and defined scope: Translate the client requirements into measurable deliverables, acceptance criteria and priorities for time, cost, quality and safety. Define interfaces and exclusions so that teams do not plan incompatible versions of the project.
2. Logical work breakdown: Divide the project into manageable work packages and activities. Assign accountable owners, establish dependencies and arrange the work in a technically feasible sequence. Coordinate design releases, permissions, procurement and execution.
3. Realistic information and resources: Use credible quantities, production rates, calendars, crew strengths and equipment availability. Include access, work-front, weather and material constraints instead of assuming that every activity can proceed simultaneously.
4. Coordination and participation: Involve design, procurement, construction and specialist teams. State who provides each input and when. Communicate the approved plan in a form that supervisors and subcontractors can use.
5. Flexibility and control: Allow proportionate contingency for uncertainty, assess alternatives and establish reporting dates. Compare actual performance with the baseline, investigate deviations and authorise corrective action. Update forecasts without silently rewriting historical commitments.
Advantages
Planning improves coordination, anticipates resource shortages, clarifies responsibilities and provides a basis for progress measurement. It can reduce avoidable idle time and support timely procurement, cash-flow forecasting and systematic decision-making.
Limitations
Forecasts depend on the quality of assumptions and cannot remove uncertainty. Detailed planning consumes time and skilled effort; excessive rigidity can obstruct useful changes. Poor participation, unreliable progress data or frequent uncontrolled revisions can make an apparently precise plan ineffective. The remedy is proportionate detail, regular review and accountable implementation.
EXAMINATION 2021-22 | KCE503
Q5 (2021-22)
Original Q1(c) | Section A | 2 marks
How you can calculate the earliest expected time and latest allowable occurrence time in PERT?
Answer
Use a forward pass: the earliest event time is the maximum of predecessor earliest time plus activity duration, Ej = max(Ei + t_ij). Use a backward pass: Li = min(Lj – t_ij). Set the final latest time equal to the required completion time; for an earliest-finish schedule, use its calculated finish.
Q6 (2021-22)
Original Q1(d) | Section A | 2 marks
Differentiate between event and activity.
Answer
An activity is work that consumes time and usually resources, such as excavating a foundation. An event is an instantaneous milestone marking a start or completion, such as excavation complete; it has no duration. In an activity-on-arrow network, arrows represent activities and nodes represent events. Events connect the work logically.
Q7 (2021-22)
Original Q1(e) | Section A | 2 marks
Define optimistic time and pessimistic time used in PERT.
Answer
Optimistic time (a) is the shortest reasonable activity duration under favourable conditions. Pessimistic time (b) is the longest reasonable duration under adverse conditions within the estimating assumptions. Together with most likely time m, they give te = (a + 4m + b)/6 and variance = [(b – a)/6]² in classical PERT.
Q8 (2021-22)
Original Q1(f) | Section A | 2 marks
Differentiate between activity and event.
Answer
An activity represents an operation with a duration, for example placing concrete. An event represents an instant when specified preceding work is completed, for example concrete placement complete. Activities may require crews, equipment and materials; events do not consume these resources or time. Their distinction is essential when interpreting activity-on-arrow networks.
Q9 (2021-22)
Original Q2(c) | Section B | 10 marks
Draw a bar chart and compute the total duration of the project from the data given below: Task 1: 5 days; Task 2: 3 days; Task 3: 7 days; Task 4: 2 days; Task 5: 4 days. Task 1 and 4 will be started together. Task 2 will start after completion of task 3 and task 3 will take place after task 1. Task 5 will be taken only after completion of task 3.
Answer
Use elapsed working days from time zero, finish-to-start links with zero lag, and no resource constraint. Tasks 1 and 4 start together; tasks 2 and 5 both wait for task 3.
1. Precedence and timing
| Task | Predecessor | Duration (d) | ES | EF | LS | TF |
|---|---|---|---|---|---|---|
| 1 | None | 5 | 0 | 5 | 0 | 0 |
| 2 | 3 | 3 | 12 | 15 | 13 | 1 |
| 3 | 1 | 7 | 5 | 12 | 5 | 0 |
| 4 | None | 2 | 0 | 2 | 14 | 14 |
| 5 | 3 | 4 | 12 | 16 | 12 | 0 |
Task 3 starts at 5 and finishes at 12. Task 2 then finishes at 15, while task 5 finishes at 16. Task 4 finishes at day 2 and does not govern completion.
Time-scaled bar chart; darker bars form the critical chain.
2. Check all terminal chains
1 → 3 → 2 = 5 + 7 + 3 = 15 days.
1 → 3 → 5 = 5 + 7 + 4 = 16 days.
Task 4 alone = 2 days.
Final answer. Critical chain: 1 → 3 → 5. Project duration = 16 working days. Task 2 has 1 day total float; task 4 has 14 days total float when both connect to the common project finish.
The bars indicate time intervals, so an activity from 0 to 5 occupies five working days. Do not count both boundaries as full days or add the durations of independent parallel branches.
Q10 (2021-22)
Original Q5(a) | Section C | 10 marks
A small project is composed of nine activities whose time estimates are listed in the following table:
| Activity | t0 | tp | tm |
|---|---|---|---|
| 1-2 | 5 | 10 | 8 |
| 1-3 | 18 | 22 | 20 |
| 1-4 | 26 | 40 | 33 |
| 2-5 | 16 | 20 | 18 |
| 2-6 | 15 | 25 | 20 |
| 3-6 | 6 | 12 | 9 |
| 4-7 | 7 | 12 | 10 |
| 5-7 | 7 | 9 | 8 |
| 6-7 | 3 | 5 | 4 |
- (i) Find the expected task time and their variance.
- (ii) Earliest and latest expected time of each node.
- (iii) Critical path.
Answer
Read the supplied columns carefully: the paper gives optimistic t0, pessimistic tp and most likely tm. Reorder them as a, m, b before substituting; all times are taken in the same working-day unit.
1. Activity means and variances
Expected time te = (a + 4m + b)/6; variance v = [(b – a)/6]². For activity 1-2: te = (5 + 4×8 + 10)/6 = 47/6 = 7.8333 days; v = (5/6)² = 0.6944 days².
| Activity | a | m | b | Expected time (d) | Variance (d²) |
|---|---|---|---|---|---|
| 1-2 | 5 | 8 | 10 | 7.8333 | 0.6944 |
| 1-3 | 18 | 20 | 22 | 20 | 0.4444 |
| 1-4 | 26 | 33 | 40 | 33 | 5.4444 |
| 2-5 | 16 | 18 | 20 | 18 | 0.4444 |
| 2-6 | 15 | 20 | 25 | 20 | 2.7778 |
| 3-6 | 6 | 9 | 12 | 9 | 1 |
| 4-7 | 7 | 10 | 12 | 9.8333 | 0.6944 |
| 5-7 | 7 | 8 | 9 | 8 | 0.1111 |
| 6-7 | 3 | 4 | 5 | 4 | 0.1111 |
Activity-on-arrow network; edge labels are expected durations in days.
2. Event timing
Forward pass: Ej = max(Ei + t_ij). Backward pass: Li = min(Lj – t_ij), with E_1 = 0 and L_7 = E_7. Keep exact fractions until the final display.
| Event | Earliest E (d) | Latest L (d) | Slack L – E (d) |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 7.8333 | 16.8333 | 9 |
| 3 | 20 | 29.8333 | 9.8333 |
| 4 | 33 | 33 | 0 |
| 5 | 25.8333 | 34.8333 | 9 |
| 6 | 29 | 38.8333 | 9.8333 |
| 7 | 42.8333 | 42.8333 | 0 |
3. Path checks
| Path | Expected duration (d) |
|---|---|
| 1 → 2 → 5 → 7 | 33.8333 |
| 1 → 2 → 6 → 7 | 31.8333 |
| 1 → 3 → 6 → 7 | 33 |
| 1 → 4 → 7 | 42.8333 |
Final answer. Critical path = 1 → 4 → 7. Expected project duration = 257/6 = 42.8333 days.
Under the conventional independent-activity, fixed-critical-path PERT approximation, project variance = 196/36 + 25/36 = 6.1389 days² and standard deviation = √(221/36) = 2.4777 days. This last statistic is an additional check; the required activity variances are listed above.
Q11 (2021-22)
Original Q5(b) | Section C | 10 marks
(i) Explain the concept of float and slack. Distinguish between the free, independent and interfering floats. (ii) Explain the three time estimates that are used in PERT. How are the expected duration of a project and its standard deviation calculated.
Answer
Float measures the scheduling freedom of an activity; slack measures the allowable movement of an event. Both depend on the chosen network, durations and completion target. They are calculated after forward and backward passes and must be reconsidered when the programme changes.
(i) Activity floats and event slack
| Quantity | Expression for activity i-j, duration d | Meaning |
|---|---|---|
| Total float | Lj – Ei – d | Delay without extending the scheduled project finish |
| Free float | Ej – Ei – d | Delay without moving the successor event beyond its early time |
| Independent float | max(0, Ej – Li – d) | Delay available between late predecessor and early successor events |
| Interfering float | Total float – free float | Part of total float whose use can delay successors |
| Event slack | Li – Ei | Difference between late and early occurrence of an event |
For Ei = 2, Li = 3, Ej = 7, Lj = 9 and d = 4 days, TF = 3, FF = 1, independent float = 0 and interfering float = 2 days. Event i has one day of slack. Do not add every activity float together; connected activities can share the same scheduling allowance.
(ii) PERT estimates and project statistics
1. Three estimates: Optimistic time a assumes favourable execution; most likely time m represents normal conditions; pessimistic time b represents adverse conditions within the stated assumptions. Estimate these for the same activity scope and time unit.
2. Activity statistics: Expected duration te = (a + 4m + b)/6. Classical PERT activity variance is v = [(b – a)/6]², and activity standard deviation is (b – a)/6.
3. Project statistics: Use expected activity durations to find the critical path. Its duration is the sum of means on that path. Under the conventional independent-activity approximation, add its activity variances and take the square root to obtain project standard deviation.
This approximation can be inaccurate when paths have similar lengths, criticality changes or durations are correlated. State these assumptions instead of claiming an exact project completion distribution.
EXAMINATION 2022-23 | KCE503
Q12 (2022-23)
Original Q1(f) | Section A | 2 marks
What are project life cycle with example?
Answer
The project life cycle is the sequence from identifying a need to completing, handing over and closing the project. For a school building, it includes feasibility and approval, design and planning, procurement, construction, testing and handover, and closeout. Each phase produces information or completed work needed for the next decision.
Q13 (2022-23)
Original Q2(c) | Section B | 10 marks
Draw with the help of mile stone chart work division structure.
Answer
A work breakdown structure, or WBS, divides the complete project scope into progressively smaller deliverables and work packages. A milestone chart then places selected completion or approval events on a time scale. The two views are related, but a WBS is a scope hierarchy rather than a programme.
Illustrative building work division
Illustrative WBS and milestone chart; example dates are not examination data.
| Level | Division | Example work package |
|---|---|---|
| 1 | School building project | Complete approved project scope |
| 2 | Substructure | Excavation, footings and plinth |
| 2 | Superstructure | Columns, beams, slabs and masonry |
| 2 | Services | Water, drainage and electrical installation |
| 2 | Finishes and closeout | Plaster, flooring, testing and handover |
1. Decompose all deliverables: Start with the complete building, then identify major elements, locations or systems. Break each into packages that can be measured, estimated and assigned. Avoid overlap and make sure that the packages together cover the authorised scope.
2. Assign management information: Give each package an identifier, owner, acceptance criterion, quantity and relevant resource assumptions. Link it to design and procurement inputs. A package may need several schedule activities; it is not automatically a single bar.
3. Select observable milestones: Choose decision or completion events such as design approved, foundation accepted, roof complete and handover achieved. A milestone has zero duration; the preceding activities consume time.
Illustrative milestone chart
| Milestone | Target week | Completion evidence |
|---|---|---|
| Design approved | 2 | Approved drawing issue |
| Foundations complete | 6 | Inspection and accepted measurements |
| Roof complete | 12 | Structural completion record |
| Services tested | 17 | Test records |
| Handover | 18 | Acceptance and handover documents |
Place each milestone as a diamond on a weekly time axis, then compare actual and forecast dates at every review. The milestone chart summarises commitments clearly, but detailed activity logic and resources must be maintained in the supporting schedule. These example weeks are illustrative, not data supplied by the examination.
Q14 (2022-23)
Original Q3(a) | Section C | 10 marks
Write the classification of scheduling. How can you calculate the earliest expected time and latest allowable occurrences time in PERT.
Answer
Scheduling translates a construction plan into timed activities, milestones and resource requirements. Its classification depends on the management purpose, level of detail and method of representation; there is no single compulsory classification for every project.
Common classifications
1. By planning level: A master schedule covers major phases and contractual milestones. A phase or package schedule develops the relevant work in greater detail. A short-term or look-ahead schedule coordinates immediately executable work and removes constraints before crews are committed.
2. By scheduling method: Bar or Gantt charts display activities against time. Milestone charts show key completion events. Network methods, including CPM and PERT, explicitly represent precedence and allow early times, late times and float to be calculated.
3. By resource treatment: An initial time schedule may assume unlimited resources. Resource smoothing rearranges activities within available float while retaining the target finish where feasible. Resource-constrained scheduling respects capacity and may require a later completion date.
Calculating PERT event times
4. Convert estimates to expected durations: Where optimistic, most likely and pessimistic times are supplied, calculate te = (a + 4m + b)/6 for each activity. Use these expected times consistently in the network and state the working-time calendar.
5. Forward pass: Set the starting event to zero. For every following event j, calculate Ej = max(Ei + t_ij) over all incoming activities. The maximum is necessary because the event cannot occur before every required predecessor is complete.
6. Backward pass: For an earliest-finish schedule, set the final latest event time equal to the calculated finish. Work backwards using Li = min(Lj – t_ij). The minimum preserves all successor requirements.
Event slack is Li – Ei. Check that all events are connected correctly and all activities satisfy their precedence constraints. A separately imposed completion target changes latest times and may produce negative float.
Q15 (2022-23)
Original Q3(b) | Section C | 10 marks
Figure shows the represents the network of a project and duration of each activity in number of days is given along the respective activity. Identify all the paths through the network and find out the critical path and project duration.
Answer
Use the activity durations printed on the supplied diagram. In particular, activity I runs from event 5 to event 6 and takes 2 days. The forward-pass start is E_1 = 0.
Drawing for Q15 (2022-23) – clean redraw of original Q3(b)
1. All complete start-to-finish paths
| Path | Sum of durations (days) | Total (d) |
|---|---|---|
| 1 → 2 → 4 → 8 | 3 + 6 + 9 | 18 |
| 1 → 3 → 4 → 8 | 4 + 4 + 9 | 17 |
| 1 → 3 → 6 → 7 → 8 | 4 + 2 + 11 + 11 | 28 |
| 1 → 3 → 5 → 6 → 7 → 8 | 4 + 7 + 2 + 11 + 11 | 35 |
| 1 → 3 → 5 → 7 → 8 | 4 + 7 + 7 + 11 | 29 |
2. Forward and backward checks
| Event | E (d) | L (d) | Slack (d) |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 3 | 20 | 17 |
| 3 | 4 | 4 | 0 |
| 4 | 9 | 26 | 17 |
| 5 | 11 | 11 | 0 |
| 6 | 13 | 13 | 0 |
| 7 | 24 | 24 | 0 |
| 8 | 35 | 35 | 0 |
At event 6, E_6 = max(E_3 + 2, E_5 + 2) = max(6,13) = 13 days. At event 8, take the maximum of the incoming finishes, not their sum.
Final answer. Critical path = 1 → 3 → 5 → 6 → 7 → 8, corresponding to B-F-I-H-K. Project duration = 4 + 7 + 2 + 11 + 11 = 35 days.
Only complete directed paths from the start event to the terminal event are compared. A route cannot travel backwards along an arrow. The critical path is the longest-duration feasible route, rather than the one containing the most activities.
EXAMINATION 2023-24 | KCE503
Q16 (2023-24)
Original Q1(e) | Section A | 2 marks
Write the phases of project cycle.
Answer
The phases are initiation and feasibility, design and detailed planning, procurement, construction and control, testing and commissioning, and handover and closeout. For example, a building moves from a justified need through approved drawings and contracts to completed, tested facilities. The phases may overlap under the selected project delivery arrangement.
Q17 (2023-24)
Original Q1(f) | Section A | 2 marks
What is the principle of CPM analysis?
Answer
CPM uses a precedence network to find the longest-duration path and hence the earliest possible project finish under stated assumptions. Forward and backward passes establish early and late times; their difference gives float. Zero-float activities govern the finish in an unconstrained earliest-finish schedule. A delay on this path needs recovery to avoid project delay.
Q18 (2023-24)
Original Q2(c) | Section B | 10 marks
What do you mean by Gantt chart? Explain with examples.
Answer
A Gantt chart is a time-scaled bar chart used to plan and communicate when activities start, how long they continue and when they finish. Activities are listed vertically, time runs horizontally and each activity is represented by a bar.
How to prepare and interpret it
1. Define activities and calendars: Divide the project into manageable operations and estimate realistic durations. State the working-day calendar and ensure that design information, access, labour, plant and materials can support the proposed dates.
2. Apply the sequence: Place the bars according to immediate predecessors and permitted overlaps. The left end gives start, the right end gives finish and the bar length represents duration. Add milestone diamonds for significant zero-duration events.
3. Example of a small foundation package: Assume setting out occupies days 0-2, excavation days 2-6, blinding days 6-7 and footing concrete days 7-10. Reinforcement procurement can run during days 0-5 but must be complete before its installation activity begins. The shown construction chain finishes on day 10.
Example time intervals
| Activity | Start | Finish | Duration |
|---|---|---|---|
| Setting out | 0 | 2 | 2 d |
| Excavation | 2 | 6 | 4 d |
| Blinding | 6 | 7 | 1 d |
| Footing concrete | 7 | 10 | 3 d |
| Procurement, parallel | 0 | 5 | 5 d |
- 4. Update progress: Show the review date, completed work and forecast remaining bars. Distinguish actual progress from the original baseline, record approved changes and investigate deviations before changing the forecast.
Usefulness and limitations
The chart is easy to understand, supports site coordination and provides a convenient meeting display. However, an unlinked chart does not clearly reveal the critical route, shared float or consequences of a delay. Link its activities to a CPM network for reliable dependency calculations, then check resource capacity before committing the dates. A long bar alone does not prove that an activity is critical.
Q19 (2023-24)
Original Q5(a) | Section C | 10 marks
A network diagram shown in fig. find (i) total expected time and variance for each activity (ii) find EST, LST and float (iii) Critical path and duration of project.
Answer
The supplied diagram labels each activity with te only. It does not give optimistic a, most likely m or pessimistic b values. Therefore the printed expected durations can be used for scheduling, but numerical activity variances cannot be recovered from the information given.
Drawing for Q19 (2023-24) – clean redraw of original Q5(a)
1. Expected times and variance limitation
Each printed te is retained in the table below. Classical PERT variance requires v_ij = [(b_ij – a_ij)/6]². Many different sets of a, m and b produce the same expected time, so a single mean does not determine a variance. In particular, do not assume zero variance merely because the estimates are absent.
2. Forward and backward passes
Start E_1 = 0. Use Ej = max(Ei + t_ij). This gives E_5 = max(6 + 3, 5 + 3) = 9, E_6 = max(6 + 4, 9 + 6) = 15, E_7 = max(9 + 8, 15 + 4) = 19, E_8 = max(15 + 7, 19 + 5) = 24 and E_9 = 26 days.
| Event | E (d) | L (d) | Slack (d) |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 6 | 11 | 5 |
| 3 | 6 | 6 | 0 |
| 4 | 5 | 6 | 1 |
| 5 | 9 | 9 | 0 |
| 6 | 15 | 15 | 0 |
| 7 | 19 | 19 | 0 |
| 8 | 24 | 24 | 0 |
| 9 | 26 | 26 | 0 |
3. Activity starts, finishes and float
For i-j: EST = Ei; EFT = Ei + d; LST = Lj – d; LFT = Lj; TF = Lj – Ei – d; FF = Ej – Ei – d. All entries below are days.
| Activity | te | EST | EFT | LST | LFT | TF | FF |
|---|---|---|---|---|---|---|---|
| 1-2 | 6 | 0 | 6 | 5 | 11 | 5 | 0 |
| 1-3 | 6 | 0 | 6 | 0 | 6 | 0 | 0 |
| 1-4 | 5 | 0 | 5 | 1 | 6 | 1 | 0 |
| 2-6 | 4 | 6 | 10 | 11 | 15 | 5 | 5 |
| 3-5 | 3 | 6 | 9 | 6 | 9 | 0 | 0 |
| 4-5 | 3 | 5 | 8 | 6 | 9 | 1 | 1 |
| 5-6 | 6 | 9 | 15 | 9 | 15 | 0 | 0 |
| 5-7 | 8 | 9 | 17 | 11 | 19 | 2 | 2 |
| 6-7 | 4 | 15 | 19 | 15 | 19 | 0 | 0 |
| 6-8 | 7 | 15 | 22 | 17 | 24 | 2 | 2 |
| 7-8 | 5 | 19 | 24 | 19 | 24 | 0 | 0 |
| 8-9 | 2 | 24 | 26 | 24 | 26 | 0 | 0 |
Final answer. Critical path = 1 → 3 → 5 → 6 → 7 → 8 → 9. Expected completion = 6 + 3 + 6 + 4 + 5 + 2 = 26 days.
Project variance, under the conventional fixed-critical-path and independent-activity approximation, would be v_13 + v_35 + v_56 + v_67 + v_78 + v_89. Its numerical value and project standard deviation remain undetermined until the required activity spread estimates are supplied.
Q20 (2023-24)
Original Q5(b) | Section C | 10 marks
Discuss in brief the resource allocation problem. What are the methods of solving the problem?
Answer
Resource allocation assigns limited labour, equipment, materials, work fronts or funds to scheduled activities. A precedence-feasible CPM schedule may still be impossible to execute when two activities need the same crane or their combined labour demand exceeds the available crew.
1. Define the allocation problem: Prepare the activity network, durations and resource requirements by time period. Establish working calendars, capacity limits and priorities. Separate renewable resources, such as crews, from consumable materials and financial limits.
2. Load and diagnose the schedule: Calculate the earliest-start programme and prepare resource histograms. Identify periods of excess demand and activities that share scarce resources. Verify that apparent shortages are not caused by unrealistic production assumptions or missing procurement lead times.
Methods of solution
3. Resource smoothing: Move noncritical activities within available float to reduce peaks while keeping the required finish where feasible. Observe dependencies and recognise that float may be shared; it cannot be spent independently on every connected activity.
4. Resource levelling: Respect a fixed resource capacity and revise activity starts accordingly. Completion may extend beyond the unrestricted CPM finish. Recalculate the critical sequence after each change rather than assuming that the original critical path remains controlling.
5. Priority-rule heuristics: Allocate available capacity using an expressly stated rule, such as least total float, earliest latest-start time or critical activity first. Apply a consistent tie-breaker. Such rules are practical but do not guarantee the global optimum.
6. Optimisation and alternatives: For important or complex cases, use mathematical optimisation, constraint programming or validated scheduling software. Compare additional crews, revised methods, split tasks where permitted, overtime and altered procurement against cost, safety and quality consequences.
For example, two parallel three-day lifts requiring one crane cannot both use a single crane simultaneously. Sequencing them may require six days unless another feasible method or resource is introduced. Monitor actual demand and update the allocation as site conditions change.
EXAMINATION 2024-25 | BCE503
Q21 (2024-25)
Original Q1(e) | Section A | 2 marks
Differentiate between planning and scheduling.
Answer
Planning decides the scope, method, sequence, responsibilities and resources needed to achieve project objectives. Scheduling assigns starts, finishes and durations to those activities within a calendar. For example, choosing staged foundation construction is planning; assigning excavation and concreting to particular working days is scheduling. A schedule must reflect the underlying plan.
Q22 (2024-25)
Original Q1(g) | Section A | 2 marks
Define Project monitoring.
Answer
Project monitoring is the regular collection, verification and comparison of actual progress, cost, resources and quality performance against the approved baseline. It identifies deviations and emerging risks so that managers can forecast the outcome and decide corrective action. Site measurements, inspection records and dated progress reports provide the evidence for this comparison.
Q23 (2024-25)
Original Q2(c) | Section B | 7 marks
Describe the phases of a construction project cycle in detail. Explain the activities and deliverables associated with each phase.
Answer
A construction project passes through connected phases, each producing information or completed work needed for the next decision. The phases may overlap, but their responsibilities and acceptance criteria should remain clear.
1. Initiation and feasibility: Identify the need, investigate the site and compare options. Assess technical, environmental and financial feasibility. Deliverables include the project brief, feasibility report, preliminary estimate and decision to proceed.
2. Design and planning: Develop coordinated drawings and specifications, obtain approvals and prepare the WBS, programme, budget and risk plan. Deliverables include approved design information and a baseline for execution.
3. Procurement: Prepare tender documents, evaluate offers and appoint contractors and suppliers. Deliverables include contracts, procurement schedules and agreed responsibilities.
4. Construction and control: Execute the work, inspect quality and compare actual time and cost with the baseline. Deliverables include completed work, measurement records and approved change records.
5. Commissioning and closeout: Test systems, remedy defects, obtain acceptance and transfer operating information. Deliverables include test certificates, as-built drawings, manuals, final accounts and handover records. Lessons learned support future projects.
Q24 (2024-25)
Original Q5(a) | Section C | 7 marks
Draw a bar chart and compute the total duration of the project from the data given below: Task 1: 6 days; Task 2: 3 days; Task 3: 7 days; Task 4: 2 days; Task 5: 4 days. Task 1 and 4 will be started together. Task 2 will start after completion of task 3 and task 3 will take place after task 1. Task 5 will be taken up only after completion of task 3.
Answer
Use elapsed working days from time zero, finish-to-start links with zero lag, and no resource constraint. Tasks 1 and 4 start together; tasks 2 and 5 both wait for task 3.
1. Precedence and timing
| Task | Predecessor | Duration (d) | ES | EF | LS | TF |
|---|---|---|---|---|---|---|
| 1 | None | 6 | 0 | 6 | 0 | 0 |
| 2 | 3 | 3 | 13 | 16 | 14 | 1 |
| 3 | 1 | 7 | 6 | 13 | 6 | 0 |
| 4 | None | 2 | 0 | 2 | 15 | 15 |
| 5 | 3 | 4 | 13 | 17 | 13 | 0 |
Task 3 starts at 6 and finishes at 13. Task 2 then finishes at 16, while task 5 finishes at 17. Task 4 finishes at day 2 and does not govern completion.
Time-scaled bar chart; darker bars form the critical chain.
2. Check all terminal chains
1 → 3 → 2 = 6 + 7 + 3 = 16 days.
1 → 3 → 5 = 6 + 7 + 4 = 17 days.
Task 4 alone = 2 days.
Final answer. Critical chain: 1 → 3 → 5. Project duration = 17 working days. Task 2 has 1 day total float; task 4 has 15 days total float when both connect to the common project finish.
The bars indicate time intervals, so an activity from 0 to 5 occupies five working days. Do not count both boundaries as full days or add the durations of independent parallel branches.
Q25 (2024-25)
Original Q5(b) | Section C | 7 marks
Classify float in a network. Explain its significance and how it can be calculated in a PERT/CPM network.
Answer
Float expresses permissible activity movement under the stated network and completion target. For an activity i-j of duration d, let E and L denote early and late event times.
1. Total float: TF = Lj – Ei – d = LS – ES. It is the delay available without extending the scheduled project finish, provided the remaining network is respected.
2. Free float: FF = Ej – Ei – d. It is the delay available without delaying the earliest occurrence of the succeeding event.
3. Independent float: IF = max(0, Ej – Li – d). It is available when the preceding event occurs at its latest time and the following event remains at its earliest time.
4. Interfering float: IntF = TF – FF. Using it can delay successors even though the project finish remains protected.
Event slack is Li – Ei and belongs to an event rather than an activity. For Ei = 2, Li = 3, Ej = 7, Lj = 9 and d = 4 days: TF = 3, FF = 1, IF = 0 and IntF = 2 days. Float is shared along connected logic; recalculate it after changes.